Valley Park is a large open space area of 40+ acres that was donated to the town of Middletown more than fifteen years ago. At the time, there was support to create a Town Center area with open space, commercial property along the road and a gathering spot for the Town. Some of the more ambitious plans were abandoned because of cost, but there was still hope the area could become an area that could be used by the town residents for outdoor activities.

Soon however, contamination of the soil from agriculture and industrial use was detected, the Rhode Island Department of Environmental Management (DEM) became involved and all plans for use of the property were halted.

After extensive engineering and environmental studies and years of negotiations by the Town Administration with DEM, an agreement was reached that allowed for the creation of specially constructed walkways  throughout the area which would serve as a cap for the contamination.

Natural vegetation will be allowed to grow around the walks which will encourage walkers to remain on the walkways and it  will only be cut once each year so that the park will remain in as natural a state as possible.

The Landscaping Plan

The Middletown Tree Commission was honored by the Town with the task of designing and implementing a landscaping plan for Valley Park. Due to the environmental constraints and other issues, the plan consists of trees alone.

The design effort began in 2015 when, together with Middletown DPW personnel, over a mile of walking trails were laid out. In the summer of 2016, crews from the DPW constructed about a mile and a quarter of trails to RI DEM specifications with gravel trucked in from Tiverton, laid over barrier sheet material.

In addition to the trails, a parking lot  was constructed on the northern end of the park, previously planted trees were moved, several other entrances were created off High Street and wooden three rail fences were installed.

An Aerial photo of the park the and walkways  looking north, taken by Gary Paquette in December of 2016, is shown below. High Street is shown along the left of the park.

The tree plantings are based on the design of Alan Kirby (Middletown Tree Warden) and Chuck DiTucci, both members of the Commission.

The planting design is shown in the link below. It consists of 11 “planting beds” which are  basically islands of trees among the natural vegetation.

Planting Overview

The planting will be done in several phases. The first phase was scheduled and completed in the  spring and summer of 2017.

Earlier that year, competitive bids were requested from 18 vendors and  5 responses were received. The list of trees in the RFQ package for that year can be seen on this page http://tree-commission.middletownri.com/request-for-proposals/   . It is on this site, and it consisted of 128 trees, of many species of both broad leaf deciduous and coniferous trees.

The winning bidder, Yardworks was selected on April 27, and as mentioned above, the effort was completed in the summer of 2017.

At the time of this writing (March, 2018 ), the RFP for the second phase has been issued and awarded to Boulevard Nurseries.   Due to budget constraints, the number of trees to be planted will be less than in the first phase, and by design, of different varieties. The total bid package can be seen on this website and subsequent pages at  http://tree-commission.middletownri.com/request-for-proposals-valley-park-phase-2/

Most of the funding for this project comes from the Town. For the first phase, the commission  also received  generous funding  from Charlie Silvia of the Newport Horticultural Society and the Alice B Mayer Trust.

Committed funding for the second phase is from the Town, the Alice B Mayer Trust and the van Bueren Charitable Foundation.

This extensive effort is a multiyear project and progress will be reported on this site.